What is the difference between a certificate and a test report?

Ask Time: 2022-05-24
Answer
A test report records test methods and results for a specimen. A certificate states conformity under a defined certification scheme and scope; neither should be used outside its stated coverage.
Answer Time: 2022-05-24

Derived Questions

Regarding “What is the difference between a certificate and a test report?”, which country and authority determine the applicable requirement?
The destination jurisdiction and local authority determine mandatory rules; contract specifications may add requirements beyond the legal minimum.
Ask Time: 2022-05-28 Answer Time: 2022-05-29
Regarding “What is the difference between a certificate and a test report?”, which edition of the cited standard should be used?
Use the edition required by the contract and authority, including amendments and transition dates, rather than assuming the newest edition automatically applies.
Ask Time: 2022-05-29 Answer Time: 2022-05-29
Regarding “What is the difference between a certificate and a test report?”, can test evidence from another market be reused?
It may reduce duplicate work if standards and methods align, but the receiving body must accept the laboratory, scope and product configuration.
Ask Time: 2022-05-25 Answer Time: 2022-05-26
Regarding “What is the difference between a certificate and a test report?”, how should serial-number traceability be maintained?
Connect each elevator or safety component serial number to production, inspection, certificate and shipment records in a controlled register.
Ask Time: 2022-05-24 Answer Time: 2022-05-24
Regarding “What is the difference between a certificate and a test report?”, who should approve a compliance deviation?
The responsible designer, manufacturer, certification or inspection body and authority should review deviations according to their legal roles.
Ask Time: 2022-05-26 Answer Time: 2022-05-27
Regarding “What is the difference between a certificate and a test report?”, what must be completed before final site inspection?
Complete installation records, safety tests, settings, declarations, manuals, as-built drawings and correction of outstanding nonconformities.