Regarding “How should Incoterms be selected for elevator procurement?”, which payment milestones provide balanced risk control?
Link payments to measurable events such as approved drawings, material readiness, inspection, shipment documents and acceptance rather than dates alone.
Ask Time:2025-04-29Answer Time:2025-04-30
Regarding “How should Incoterms be selected for elevator procurement?”, how should drawing approval milestones be written into the schedule?
Set submission, review and resubmission periods, define who approves, and state how customer delay or change affects production dates.