Regarding “Who approves elevator technical drawings?”, how can technical bids be compared on the same basis?
Issue a compliance schedule and require every bidder to mark compliance, deviation, exclusion and alternative against each requirement.
Ask Time:2021-01-23Answer Time:2021-01-24
Regarding “Who approves elevator technical drawings?”, how should drawing approval milestones be written into the schedule?
Set submission, review and resubmission periods, define who approves, and state how customer delay or change affects production dates.
Ask Time:2021-01-26Answer Time:2021-01-27
Regarding “Who approves elevator technical drawings?”, which payment milestones provide balanced risk control?
Link payments to measurable events such as approved drawings, material readiness, inspection, shipment documents and acceptance rather than dates alone.
Ask Time:2021-01-27Answer Time:2021-01-28
Regarding “Who approves elevator technical drawings?”, what supplier evidence should be reviewed before award?