Freeze requirements early, provide complete shaft data, set approval deadlines, track long-lead items and coordinate payment, inspection and shipping milestones.
Answer Time:2022-04-06
Derived Questions
Regarding “How can elevator procurement delays be prevented?”, how can technical bids be compared on the same basis?
Issue a compliance schedule and require every bidder to mark compliance, deviation, exclusion and alternative against each requirement.
Ask Time:2022-04-10Answer Time:2022-04-10
Regarding “How can elevator procurement delays be prevented?”, which quotation exclusions often create later cost increases?