What information is needed to request an elevator quotation?

Ask Time: 2021-01-25
Answer
Provide project location, building use, quantity, floors, travel, capacity, speed, shaft dimensions, entrances, standards, finishes and delivery expectations.
Answer Time: 2021-01-25

Derived Questions

Regarding “What information is needed to request an elevator quotation?”, which payment milestones provide balanced risk control?
Link payments to measurable events such as approved drawings, material readiness, inspection, shipment documents and acceptance rather than dates alone.
Ask Time: 2021-01-31 Answer Time: 2021-01-31
Regarding “What information is needed to request an elevator quotation?”, how can technical bids be compared on the same basis?
Issue a compliance schedule and require every bidder to mark compliance, deviation, exclusion and alternative against each requirement.
Ask Time: 2021-01-27 Answer Time: 2021-01-28
Regarding “What information is needed to request an elevator quotation?”, what supplier evidence should be reviewed before award?
Review comparable references, factory capability, quality controls, certificates, engineering team, testing, traceability and after-sales resources.
Ask Time: 2021-01-30 Answer Time: 2021-01-30
Regarding “What information is needed to request an elevator quotation?”, how should drawing approval milestones be written into the schedule?
Set submission, review and resubmission periods, define who approves, and state how customer delay or change affects production dates.
Ask Time: 2021-01-30 Answer Time: 2021-01-30
Regarding “What information is needed to request an elevator quotation?”, which project data should be fixed before issuing the RFQ?
Freeze location, use, quantities, travel, stops, shaft geometry, capacity, speed, doors, standards, finishes, interfaces and required dates.
Ask Time: 2021-01-26 Answer Time: 2021-01-27
Regarding “What information is needed to request an elevator quotation?”, which quotation exclusions often create later cost increases?
Check freight, duties, installation, testing, certification, builder’s work, power, scaffolding, tools, travel, commissioning and spare parts.